Requirement :
|
Balance work for earthwork in cutting and filling with mechanical compaction, supplying, spreading and compaction of stone dust blanketing, construction of major bridge no.33 (1 x 61.00m open web girder, the girder will be supplied by railway), br.no.31 (rub), remaining work of other minor bridges, construction of new platform wall, retaining wall, linking of track & points & crossing, supplying, stacking & spreading of machine crushed stone ballast on cess, transporting of p.way materials and fabricated girder components, approach station road at sondalia and beliaghata road, construction of station building at sondalia, fob & pf shed at beliaghata road, miscellaneous protection work and other ancillary works including remodeling of both the yards for doubling between stations sondalia (including) (km 12.120) and lebutala (including) (km 18.070) in connection with doubling between sondalia & .
|