Requirement :
|
Design, Drawing, Construction, Testing, Commissioning of Intake well, Raw Water Electric sub station i/c Raw water pumps and motors, Water Treatment Plant, Clear water Electric sub station i/c clear water pumps and motors, MBRs, Providing, laying, jointing and testing & commissioning of Raw water & Clear water Pumping Main of DI K-9 pipe, Clear Water Gravity main of DI K-7 & O-PVC pipes with all required valves & specials, with all allied civil works including boundary wall around WTP campus and 03 Nos. MBR’s and CC road inside WTP Campus to fasicilate for movement of goods and materials, providing and fixing Bulk flow meters, including testing of Entire scheme for 03 months after completion of all components of the scheme including chemicals, staff and trial run of entire scheme for 09 months with defectliabilities period of 1 year under 48 Villages of Multi Village water supply scheme Kalma-Kodatarai Block Pusore, District (C.G.)
|